Work in progress - June 2023

This month we are excited to unveil our continued progress within our community. As new residents receive their bespoke homes, we finalize details on surrounding amenities and green areas, ensuring that every element harmonizes with our intentional designs. Using dynamic creative processes we supervise daily advances, optimizing lighting, pathways, vegetations, and decor to create stunning results. As we enter the rainy season we make sure to take advantage of the local climate to test irrigation and site levels as well as waterproofing in all construction areas.

Its summertime in Tulum! As we work through the extreme heat and tropical rains we take extra care to provide hydration and mandatory breaks to all of our workers onsite. We are thankful to finally open access to our stunning central semi-olympic pool. With over a dozen units delivered to investors, it brings us great joy to see our unique amenities and come to life with the presence of our newly forming community.

This month we have begun even more artistic interventions with the addition of the unique sculptures of Bacalar-based artist Abraham Illescas. His massive rock and wooden installations and add to Aflora's playful ambience and inspire our sense of wonder and imagination.

Aflora Tulum Panza Restaurant art, black wood sculptures by Abraham Illescas

Construction Progress

Work continues on Aflora. We summarize the major advances in each area below

Aflora Tulum Aerial Photo - July 2023


Loft Village

Loft Village: Construction progress - 99% Complete


Essence Luxury Villas

Villa 1: Construction progress - 100% Complete | Villa 5: Construction progress - 32% Complete


Magic Apartment Towers

Tower B:
Construction progress -85% Complete

  • Detailing on exterior elements

  • Drainage installation and waterproofing in rooftop gardens

  • Installation of bathroom tile and toilets

  • Carpentry in progress

  • Installation of machine rooms and pool equipment

      

Tower D:
Construction progress - 55% Complete

  • Roof-level installations in progress

  • Rooftop pools and gardens in progress

Tower H:
Construction progress - 42% Complete

  • Walls and columns in progress on level 3

    Elevator shaft in progress on level 3

Tower A: Construction progress - 86% Complete

  • Preparations for final finish in interiors and exteriors 

  • Installation of garden-level cobblestone blocks

  • Installation of rooftop pergolas and built-in gardens 

  • Installation of carpentry

  • Installation of final floor in circulations areas and stairs

Tower C:
Construction progress - 67% Complete

  • Terrace railings installed

  • Detailing and waterproofing on rooftop levels

  • Structural detailing on terraces

Tower I:
Construction progress - 52% Complete

  • Electrical installations on level 1

  • 4th level walls roof in progress

  • Installations on lower levels in progress

  • Rooftop pools in progress


Amenities

Semi-Olympic Pool:
Construction progress - 100%

Panza (Restaurant):
Construction progress - 99%

Lobby:
Construction progress - 100%

Wellness Tower:
Construction progress - 70% Complete  

  • Application of interior and exterior finishes

  • Lower-level floors poured

  • Installations on lower and upper levels in progress

Natural Pool:
Construction progress - Awaiting final installations

  • Construction of stone steps and retaining walls made from material sourced on-site

  • Waterfall testing completed

BathHouse & Spa:
Construction progress - 10%

  • Lower-level walls poured

  • Lower-level installations in progress

Service Areas & Bodegas:Construction progress - 80% Complete   

  • Testing of installations in progress

  • Server rooms completed and equipment installed

  • Security site completed and operational

  • Doors and windows installed

  • Climate control in progress


Green Initiative

We received positive news this month regarding rehabilitation efforts for sea turtles, for the first time in 36 years of conservation, a leatherback has been seen laying eggs on the Tulum municipal beach.

The discovery was made within the state preserve of Xcacel-Xcacelito Sea Turtle Sanctuary, where a total of 54,214 white/green turtle nests and 9,030 loggerhead turtle nests have been recorded from 1996 to 2022. In addition, a total of of 4,770,850 white/green turtles and 711,891 loggerhead turtle hatchlings have been located.

The leatherback sea turtle is the largest in the world weighing between 249 and 907 kilos and growing up to 1.8 meters in length.

Community News

Tulum received official approval of 11 million pesos dedicated to the paving and improvement of municipal roads. With our city-grid expanding faster than urbanization efforts can keep up with, this will bring a much-needed modernization to Tulum's image and mobility. This month Tulum also successfully settled all outstanding municipal debts totaling nearly 70 million pesos and dating back to 2015.

This positive news coincides with a significant drop in violent crime thanks to increased coordinated efforts between National Guard, National Defense and Navy as well as the State Attorney General’s Office, Public Security of Tulum and the state, to ensure peace in the municipality.

Previous
Previous

Work in progress - July 2023

Next
Next

Work in progress - May 2023