November 2022 News

Hello Aflora Community! We are excited to enter another holiday high-season in Tulum as both tourism and local occupancy rates begin to rise. While much of the world is preparing for a cold winter, we are enjoying perfect conditions as beaches and seas are clear and calm. The final units of Phase 1 are moving quickly with end-of-the-year discounts in effect. Aflora investors are now able to receive up to 4% additional discounts on the purchase of additional units.

Onsite, we are rapidly advancing to make-up for time lost to material and labor shortages. Thankfully we are beginning to receive our orders of delayed materials and equipment as global supply chains begin to recover. With all phases currently in progress, we are able to exert power in numbers on key areas that are first in line to be completed.

 From unique handcrafted tile to bespoke cabinetry, we begin to see Aflora’s living spaces come to life as they receive their final finishes. Our design teams work day and night testing materials and ambience in all lighting conditions. Undeterred by minor delays, we are proud to see the vision of a unique community based around nature and art become a reality.

 
 

Construction Progress

Work continues on all key areas of Aflora. We summarize the major works ongoing in each area below

 

Loft Village:
Construction progress - 88% Complete

  • Installation of condenser units for air conditioners

  • Acrylic treatment of rooftop areas

  • Bases for railings and shading on private terraces

  • Tile installation in showers

  • Sheetrock ceilings painted

  • Installation of Kitchen cabinets

  • Installation of Closets

  • Elevator mounted and installed

  • Exterior lighting (testing underway)

  • Concrete base of reflecting pool constructed

 
 
 

Villa 1:
Construction progress - 84% Complete

  • Garden walls underway

  • Final interior finishes

  • Air conditioning equipment installed

  • Steel supports for doors and gates installed

 

Magic Apartment Towers

Tower C:
Construction progress - 50% Complete

  • Stairway between 3rd and 4th levels completed

  • 3rd level floors poured

  • 4th level structural elements underway

  • Ongoing masonry on final levels

  • Installations on lower levels

Tower D:
Construction progress - 22% Complete

  • 2nd level floors poured

  • 1st level installations in progress

  • Structural preparations for upper levels

Tower I:
Construction progress - 17% Complete

  • 1st level walls underway

  • Structural preparations for upper levels

Tower A:
Construction progress - 74% Complete

  • External treatments for final finishes underway

  • Internal treatments for final finishes underway

  • Site cleaning and testing of installations

  • Filling and leveling of material in garden and pool areas.

  • Installations of Roof Gardens

  • Rehabilitation of Green Areas in surrounding vicinity

Tower B:
Construction progress - 76% Complete

  • External treatments for final finishes underway

  • Internal treatments for final finishes underway

  • Site cleaning and testing of installations

  • Installations of Roof Gardens

  • Installation of Rooftop Pergolas

  • Filling and leveling of material in garden and pool areas.

 
 

Service Areas & Bodegas:
Construction progress - 40% Complete 

  • Walls and structural elements completed

  • Support structure for roof in progress

  • Installations of electrical and hydro sanitary in progress

Semi-Olympic Pool:
Construction progress - Awaiting final finish

  • All preliminary works completed and tested

  • Awaiting the termination of construction to apply final EKOL finish to prevent accidental damage or wear.

Natural Pool:
Construction progress - Awaiting final installations

  • Extended depth (up to 6 meters deep)

  • Natural circulation system to decrease maintenance costs

  • In-person direction of excavations from local experts in natural pools

BathHouse & Spa
Construction progress - Undergoing Modifications 

  • Modification of construction technique in response to soil conditions and surrounding water levelService Areas & Bodegas:
    Construction progress - 40% Complete 

    • Walls and structural elements completed

    • Support structure for roof in progress

    • Installations of electrical and hydro sanitary in progress

Lobby:
Construction progress - 90% Complete

  • Final cement finish on stairs and

  • Sunset tower floor

  • Preparations for dynamic art installation

Panza (Restaurant): 
Construction progress - 78% Complete

  • Non-slip tile flooring installed in Kitchen areas

  • Glass domes on dining area pergola installed

  • Installation of bar and open kitchen area

Wellness Tower:
Construction progress - 58% Complete 

  • 2nd level access stairs in progress

  • 2nd level structure in progress

  • Rehabilitation of Green Areas in surrounding vicinity

Frontal Sculptural Wall:
Construction progress - 65% Complete 

  • Created from solid concrete poured into hand-built forms

  • Section 1 complete

  • Section 2 in progress

 
 

Green Initiative

This November Aflora is getting greener than ever as we begin to landscape the integrated gardens in residential areas and amenities. With integrated drainage and drip systems, Aflora’s living spaces will be carefully adorned with native vegetation suitable for their unique location.

 

These organic installations will not only create a vibrant and lush atmosphere, but will also provide shade and privacy to residential areas. We will soon conclude testing on all garden installations and advance to the integration of local species. 

Community News

This month Tulum received a visit from Mexican President Andrés Manuel López Obrador to personally announce details on upcoming projects and initiatives including the Maya Train and Tulum International Airport, both of which are currently undergoing important environmental impact surveys. The announcement concluded with news that within weeks we will be receiving official inauguration dates of these major initiatives.

 

As local businesses prepare for the impending high season, we have seen significant advances in public works projects including the improvement of key roads and the integration of stoplights and crosswalks in busy intersections. Return visitors will be pleased to find a safer, cleaner Tulum as we move closer to our vision of a sustainable future. 

 