With over 300 workers onsite daily we see the magic unfold when many hands work together toward a common goal. From our in-house engineers and supervisors to subcontractors from across the country, we are tremendously proud to be part of this great endeavor that will soon fulfill its purpose of a unique community in Tulum built around art & nature.
Construction progress
As we near the end of this year we are excited to take you in depth into our construction advances. Aflora is a multifaceted community, thus we will take you through each area of your future home in the jungle
Loft Village:
Construction progress - 84% Complete
Application of COREV (final exterior finish) on all facades
Finalizing waterproofing in upper areas and built-in gardens
Testing handrails and shade panels
Sheetrocking ceilings
Cabling and wiring finished
Installations for onsite laundry area
Preparations for final urbanization and connections of electrical and hydro-sanitary network
Rehabilitation of Green Areas in surrounding vicinity
Villa 1:
Construction progress - 75% Complete
Application of COREV (final exterior finish) on all facades
Garden Walls
Interior stairway support steel-structure (floating stairs)
Sheetrock support structures
Cabling and wiring finished
Magic Apartment Towers
Tower A:
Construction progress - 65% Complete
Completion of all structural and masonry elements
Preparations for final finishes
Site cleaning and testing of installations
Testing of pool equipment and machinery
Rehabilitation of Green Areas in surrounding vicinity
Tower B:
Construction progress - 65% Complete
Completion of all structural and masonry elements
Preparations for final finishes
Site cleaning and testing of installations
Testing of pool equipment and machinery
Rehabilitation of Green Areas in surrounding vicinity
Tower C:
Construction progress - 44% Complete
Structural elements and masonry complete to 3rd level
Testing of installations and connections of electrical and hydro-sanitary network
Tower D:
Construction progress - 14% Complete
Foundations and cisterns completed
1st level walls underway
Structural preparations for upper levels
Tower I:
Construction progress - 14% Complete
Foundations and cisterns completed
1st level walls underway
Structural preparations for upper levels
Lobby:
Construction progress - 85% Complete
Application of COREV (final exterior finish) on interior cylinder and central office.
Preparations for dynamic art installation
Detailing on bamboo and steel support structure
Panza (Restaurant):
Construction progress - 67% Complete
Kitchen equipment and safety equipment ordered and in production
Custom wood-fired hybrid oven ordered
Installation of breeze block panels
Wellness Tower:
Construction progress - 48% Complete
Lower level structure is complete
2nd level structure in progress
Rehabilitation of Green Areas in surrounding vicinity
Frontal Sculptural Wall:
Construction progress - 50% Complete
Created from solid concrete poured into handbuilt forms
Completed from Loft Village to Lobby
Service Areas & Bodegas:
Construction progress - 32% Complete
Foundations completed
Walls and structural elements completed
Installations of electrical and hydro sanitary in progress
Semi-Olympic Pool:
Construction progress - Awaiting final finish
All preliminary works completed and tested
Awaiting the termination of construction to apply final EKOL finish to prevent accidental damage or wear.
Natural Pool
Construction progress - Undergoing Modifications
Extended depth (up to 6 meters deep)
Natural circulation system to decrease maintenance costs
In-person direction of excavations from local experts in natural pools
Bathhouse & Spa
Construction progress - Undergoing Modifications
Modification of construction technique in response to soil conditions and surrounding water level
Green Initiative
This month we tripled the staff on our onsite gardening team in order to rehabilitate areas used for construction and central access. Utilizing transplants displaced from construction areas we carefully replace native vegetation to provide privacy and shade to amenities and residences. In the process of rehabilitation we utilize organic compost created onsite to assist in the recovery of preservation areas.
We have also made significant progress this month on the preparations for our massive photovoltaic solar system that will be located on top of the Loft Village, providing electricity to all of Aflora’s common areas and amenities. Additionally Luxury Villa owners are able to integrate individual solar systems to offset personal usage.
Community News
With Tulum’s new sound ordinances in place, beach hotels are experiencing higher occupancy rates as well as some much-needed peace and quiet. Regulatory equipment and enforcement has been implemented throughout the entire beach hotel zone. This is a large win for Tulum’s Hotel Association which has been fighting for greater regulation in order to protect the delicate ecosystem and preserve Tulum’s image.
We have seen significant advances this month on Tulum’s new Jaguar National Park. This new nature preserve will include bike paths, walking trails, and over one thousand hectares of protected areas. This is an exciting step in the preservation of Tulum’s ecosystem which has been under recent stress due to the explosive demand in tourism in the region.
As we move into the holiday season, we give special thanks to our longtime supporters and early investors whose belief in Aflora has elevated us to where we are today. We are working diligently alongside our Post Sales Team to streamline legal closing processes and ensure each unit delivery is handled with the utmost care.