Work in progress - August 2023
This month in Aflora we continue to make significant progress on our residences despite heavy seasonal rainfall as we deliver finished units to our investors. We are excited to present our fast-growing community of onsite residents and guests with an official Condominium Administration team which will be taking over the operation and upkeep of common areas in the weeks to come. With this, we will also be providing our investors with an exciting Vacation Rental Administration program that allows for convenient and transparent services while providing unmatched benefits and results. Please stay tuned for these important announcements in the month of September.
Construction Progress
Work continues on Aflora. We summarize the major advances in each area below
Wonder Loft Village
Loft Village: Construction progress - 99% Complete
-61 of 68 units delivered to interior design team
-Co-working area final floors installed
-Detailing in access points
-Laundry area ready for machinery
Essence Luxury Villas
Villa 5: Construction progress - 50% Complete
-Installation of plumbing and electrical ducts of level 3 & rooftop
-Rooftop pool completed
-Garden walls in progress
Magic Apartment Towers
Tower B:
Construction progress - 90% Complete
-Detailing on exterior elements
-Testing of air conditioner equipment
-Installation of accessories in bathrooms
-Carpentry in progress
-Installation of electrical switches and contacts
Tower D:
Construction progress - 59% Complete
-Electrical connections in progress
-Level 2 walls in progress for finishes
Tower H:
Construction progress - 53% Complete
-Machine rooms for pool equipment in progress
-Preparations for sanitary connections in progress
-Rooftop level walls in progress
Tower A: Construction progress - 91% Complete
-Connections of air-conditioning equipment
-Installation of electrical switches and contacts
-Installation of accessories in bathrooms
-Final finishes in private pools
Tower C:
Construction progress - 72% Complete
-Sheetrock structures in progress
-Preparations for air conditioning equipment
-Preparations for exterior finishes in progress
Tower I:
Construction progress - 57% Complete
-Hydro-sanitary connections on level 1
-Roof garden walls in progress
Amenities
Semi-Olympic Pool:
Construction progress - 100%
Panza (Restaurant):
Construction progress - 100%
Lobby:
Construction progress - 100%
Wellness Tower:
Construction progress - 75% Complete
-Lower-level interior walls completed
-Installations on lower and upper levels in progress
-Gym equipment orders in progress
Natural Pool:
Construction progress - Awaiting final installations
Construction of stone paths and viewpoints
Waterfall in operation
BathHouse & Spa:
Construction progress - 16%
-Lower-level walls poured
-Lower-level installations in progress
-Structural preparations for secondary levels in progress
Service Areas & Bodegas:
Construction progress - 97% Complete
-Employee Kitchen and Cafeteria in progress
-Server rooms completed
-Security site completed
Green Initiative
With much anticipation Tulum has inaugurated its state-of-the-art water desalination plant located in Aldea Zama. This facility will help provide clean water to the municipality and facilitate future commercial and residential growth, the pace of which continues to accelerate year-over-year.
Community News
Two major Mexican airlines have announced ticket sales for Tulum's soon-to-be completed international airport. With Viva Aerobús announcing five flights leaving from Tulum and Aeroméxico promoting two flights daily starting December 1st of this year.
As municipal roadworks expand throughout town, new road repairs have been extended to Punta Allen, promising the improvement of the once-impassible 40km access road that runs through the Sian Kaan biosphere preserve. This will improve access to the small fishing village as well as the many access points to the beaches and reserve.