Work in progress - September 2023

This month in Aflora we are thrilled to announce our official partnership with Elite Alliance as Aflora’s official in-house Vacation Rental Administration & Hospitality Management. With three decades of industry experience, Elite Alliance stands as one of the most sought after partners among experiential luxury real estate developers and operators worldwide. Their team of experts is world-renowned for pioneering world-class developments by providing new concepts and expertise resulting in over $1B USD in sales. Our investors will be receiving information on how to join this exclusive program in a separate correspondence.


Construction Progress

Work continues on Aflora. We summarize the major advances in each area below



Wonder Loft Village

Loft Village: Construction progress - 99% Complete

-64 of 68 units delivered to interior design team
-Co-working area final floors installed
-Detailing in access points
-Laundry area ready for machinery


Essence Luxury Villas

Villa 5: Construction progress - 54% Complete

-Preparations for exterior finishes complete
-Interior installations underway for interior electrical accessories
-Garden walls in progress


Magic Apartment Towers

Tower B:
Construction progress - 95% Complete

-Installation of water softeners underway
-Installation of accent lighting in progress
-Installation of accessories in bathrooms
-Installation of cement floors and sealant

Tower D:
Construction progress - 60% Complete

-Electrical connections in progress
-Level 2 walls in progress for finishes

Tower H:
Construction progress - 53% Complete

-Machine rooms for pool equipment in progress
-Preparations for sanitary connections in progress
-Rooftop level walls in progress

Tower A: Construction progress - 94% Complete

-Testing of integrated irrigation on roof gardens
-Installation of carpentry in kitchens and washrooms
-Installation of accessories in bathrooms
-Installation of quarts counters in kitchen and washrooms

Tower C:
Construction progress - 74% Complete

-Installation of elevator in progress
-Preliminary installation of air conditioning equipment
-Exterior finishes in progress

Tower I:
Construction progress - 57% Complete

-Hydro-sanitary connections on level 1
-Roof garden walls in progress


Amenities

Wellness Tower:
Construction progress - 75% Complete
 

-Lower-level interior walls completed
-Installations on lower and upper levels in progress
-Gym equipment orders in progress

Natural Pool:
Construction progress - Awaiting final installations

Construction of stone paths and viewpoints
Waterfall in operation

BathHouse & Spa:
Construction progress - 16%

-Lower-level walls poured
-Lower-level installations in progress
-Structural preparations for secondary levels in progress

Service Areas & Bodegas:
Construction progress - 97% Complete
  

-Employee Kitchen and Cafeteria in progress
-Server rooms completed
-Security site completed


Green Initiative

Within the month of September 5,500 various trees were planted throughout 11 municipalities in the state of Quintana Roo as part of a joint effort from the Secretariat of Infrastructure, Communications and Transportation (SICT), who dug the holes, and the Quintana Roo Youth Institute and CAPA who helped to water them.

We are excited to witness the wide-ranging participation in the tree planting program with volunteers ranging from citizens, students, civil associations as well as municipal, state and federal government employees.

Community News

With major improvements underway in the Municipality of Tulum, we are happy to receive reports that the Potable Water and Sewerage Commission (CAPA) is over 50% finished in carrying out the replacement of a potable water conduction line on Coba Sur Avenue in the city of Tulum.

The replacement is being done to keep up with the demand of the growing city. The goal of the project is to build 1,257 linear meters of pipes of different diameters on Cobá Sur Avenue with its existing derivations, as well as the installation of sectioning valves and their boxes, to guarantee the correct operation of the line. This new infrastructure is valued at a total cost of 5.1 million pesos and will benefit 3,733 residents.

Previous
Previous

Work in Progress - October 2023

Next
Next

Work in progress - August 2023