Elite Alliance has long been recognized for curating an exclusive network of luxury vacation properties, and we are excited to extend the benefits of this partnership to all of Aflora! Discover how Elite can help you maximize returns on your investment, as well as vacation throughout the world while preserving the unique essence of Aflora.

Construction Progress

Work continues on Aflora. We summarize the major advances in each area below

 

Loft Village:

Construction progress - 99% Complete

  • 64 of 68 units delivered to interior design team

  • Co-working furniture installed

  • Detailing in access points and surrounding landscaping

  • Laundry machines installed

Villa 5:

Construction progress - 55% Complete

  • Electrical installations underway

  • Exterior finished in preparation

Magic Apartment Towers

Tower A:

Construction progress - 97% Complete

  • Installation of pool finishes and testing of pool equipment

  • Installation of accessories in bathrooms and kitchens

  • Installation of water heaters

  • Installation of water softening and pump systems

Tower B:

Construction progress - 95% Complete

  • Installation of water softeners underway

  • Installation of accent lighting in progress

  • Installation of accessories in bathrooms

  • Installation of cement floors and sealant

Tower C:

Construction progress - 75% Complete

  • Installation of elevator in progress

  • Installation of electrical equipment and contacts

  • Exterior finishes in progress

Tower D:

Construction progress - 61% Complete 

  • Electrical connections in progress

  • Exterior finishes in progress

Tower I:

Construction progress - 59% Complete

  • Built-in furniture in progress

  • Roof garden walls in progress

Tower H:

Construction progress - 57% Complete

  • Machine rooms for pool equipment in progress

  • Preparations for sanitary connections in progress

  • Rooftop level floors and drains in progress

Wellness Tower:

Construction progress - 80% Complete  

  • Air conditioning equipment installed

  • Windows installed 

  • Gym equipment orders en route

Service Areas & Bodegas:

Construction progress - 99% Complete  

  • Employee Kitchen and Cafeteria in progress

  • Server rooms completed 

  • Security site completed

Natural Pool:

Construction progress - Awaiting final installations

  • Construction of stone paths and viewpoints

  • Waterfall in operation

BathHouse & Spa:

Construction progress - 33%

  • Second-level diversionary walls in progress

  • Second-level installations in progress

  • Second-level steel structure in progress

Green Initiative

As we prepare to launch operations of PANZA, our onsite eatery, we are excited to participate in Tulum's recycling and compost program. We are working hand-in-hand with providers of food and beverage to minimize single-use plastics and unnecessary packing materials, favoring local providers with nearby distribution networks. 

Community News

Work continues this month on Avenida Cobá, Tulum's main beach access point. The revamped Avenue, running adjacent to Aflora, will include a bicycle lane, a pedestrian walkway, and paved access to The National Jaguar Park. 

 

Stay tuned for our upcoming list of culture events and workshops as we will soon launch happenings onsite ranging from wellness to culinary experiences!

Previous
Previous

Work in Progress - November 2023

Next
Next

Work in progress - September 2023