It has been an exciting month here in Aflora, as our Hospitality Team prepares for the launch of PANZA DINING & BAR for brunch service starting today, December 1st from 8:00 AM to 5:30 PM. We are thrilled to introduce the Aflora community to our dedicated staff and delicious creations found exclusively at PANZA.
This month we are thrilled to welcome our new Master Broker Sales Team from MAX PROPERTIES, who will be pioneering future sales of Aflora Residences, bringing with them a wonderful team of expert brokers and real estate professionals. We give special thanks to our previous sales team for the spectacular years of collaboration.
We are also thrilled to welcome our new staff for condominium administration which includes an onsite maintenance, cleaning, administrative positions, and concierge.
Construction Progress
Work continues on Aflora. We summarize the major advances in each area below
Loft Village:
Construction progress - 99% Complete
68 of 68 units delivered to interior design team
Co-working furniture installed
Co-working murals completed
Detailing in access points and surrounding landscaping
Laundry machines in tests
Villa 5:
Construction progress - 55% Complete
Electrical installations underway
Interior finishes in progress
Magic Apartment Towers
Tower A:
Construction progress - 98% Complete
Testing of video intercoms
Tests of exterior lighting on rooftops
Entrance paths and landscaping
Final details on carpentry
Interior design underway
Tower B:
Construction progress - 95% Complete
Testing of video intercoms
Installation of accent lighting
Final details on carpentry
Tower C:
Construction progress - 77% Complete
Testing of air conditioning equipment
Installation of pergolas on roof gardens
Interior finishes in progress
Tower D:
Construction progress - 61% Complete
Electrical connections in progress
Exterior finishes in progress
Tower I:
Construction progress - 61% Complete
Tests of hydraulic installations
Lighting installations in progress
Tower H:
Construction progress - 58% Complete
Exterior drains installed
Sanitary connections in progress
Lighting installations in progress
Wellness Tower:
Construction progress - 89% Complete
Cement subfloor in Gym installed
Wooden floor in yoga area in progress
Exterior paint in progress
Service Areas & Bodegas:
Construction progress - 100% Complete
Employee Kitchen and Cafeteria completed and delivered
Server rooms completed
Security site completed
Natural Pool:
Construction progress - Awaiting final installations
Construction of stone paths and viewpoints with landscaping
Additional waterfalls in progress
BathHouse & Spa:
Construction progress - 40%
Central module concrete base completed
Second-level installations in progress
Flotarium foundation in progress