Happy Holidays to our Aflora Tribe! As we near the end of an eventful year we express deep gratitude to our dedicated community and to the incredible efforts of the builders and creators that have transformed the dream of Aflora into a spectacular reality. As we push to make-up for delays our subcontractors are now operating on extended schedules, with work continuing into nights, weekends and holidays.

Our onsite supervision is present 7-days a week to ensure progress is made. 

 

Construction Progress

Work continues on all key areas of Aflora. We summarize the major work ongoing in each area below

 

Magic Apartment Towers

Tower A:

Construction progress - 79% Complete

  • Final floors poured 

  • Preparations for final finish in interiors and exteriors 

  • Detailing on exterior elements

  • Drainage installation and waterproofing in rooftop gardens

  • Installation of rooftop pergolas

  • Installation of machine rooms and pool equipment

 

Tower B:

Construction progress - 78% Complete

  • Final floors poured 

  • Preparations for final finish in interiors and exteriors 

  • Detailing on exterior elements

  • Drainage installation and waterproofing in rooftop gardens

  • Installation of rooftop pergolas

  • Installation of machine rooms and pool equipment 

 

Tower C:

Construction progress - 58% Complete

  • Rooftop pools poured

  • Rooftop level floors completed

  • Detailing on rooftop access stairs

 

Tower D:

Construction progress - 27% Complete

  • 2nd level walls in progress 

  • 1st level installations in progress

  • Structural preparations for upper levels underway

 

Tower I:

Construction progress - 21% Complete

  • Elevator shaft poured

  • 2nd level floors in progress

  • Installations on lower levels

 

Villa 1:

Construction progress - 90% Complete

  • Sheetrock installation

  • Kitchen and Closet Cabinetry 

  • Steel supports for stairs, gates, and exterior doors

  • Patios and Terraces 

Installation of oversized glass panes  

Loft Village:

Construction progress - 91% Complete

  • Polished cement interior finishes

  • Polished cement floors

  • Kitchen and Closet Cabinetry 

  • Countertops and vanity installed

  • Bathroom shower tile installation

  • Terrace shade-panels installed

  • Final detailing in Phase 1 units 

 

Lobby:

Construction progress - 92% Complete

  • Carpentry installed in upstairs office

  • Polished cement floors in office completed

  • Lighting preparations installed

  • Polished cement floors in office completed

 

Panza (Restaurant): 

Construction progress - 83% Complete

  • Kitchen extraction and counter-incendiary systems installed

  • Gas lines installed & tested

  • Craft Cocktail Bar & Open Kitchen Area constructed and awaiting the installation of wood fired oven

 

Wellness Tower:

Construction progress - 60% Complete  

  • 2nd level access stairs in progress

  • 2nd level structure in progress

  • Rehabilitation of Green Areas in surrounding vicinity 

  •  

Frontal Sculptural Wall:

Construction progress - 100% Complete  

  • Full length of perimeter completed

  • Foundations treated against moisture

  • Surrounding in-fill and landscaping underway

  • Temporary construction walls removed

 

Service Areas & Bodegas:

Construction progress - 60% Complete  

  • Walls and structural elements completed 

  • Final roof levels underway

  • Installations of electrical and hydro sanitary network completed

 

Semi-Olympic Pool:

Construction progress - Awaiting final finish

  • All preliminary works completed and tested

  • Surrounding pool deck and cobblestoned area in progress

  • Awaiting the termination of construction to apply final EKOL finish to prevent accidental damage or wear. 

 

Natural Pool:

Construction progress - Awaiting final installations

  • Dredging of fine material and debris underway with specialized SCUBA team

  • Natural circulation system to decrease maintenance costs 

  • Surrounding leveling and landscaping in progress

 

BathHouse & Spa:

Construction progress - Preliminary Site preparations 

 

Green Initiative

We are thrilled to see the results of our conservation efforts as we integrate transplanted trees and native species into their final locations, rehabilitating areas previously cleared for construction. Our in-house team of native plant specialists take extra care to integrate symbiotic species suitable environments, using composted material sourced on-site to ensure successful long-term growth.  

Community News

Big plans are underway in Tulum for the year 2023. Municipal officials announced sweeping measures to improve the excess and visitor experience at Tulum’s public beach and National Park area. With the relocation of over 170 irregular tourist-servers ranging from coconut vendors to snorkel tours, the municipality plans to add 3 additional beach access points in this year alone. 

 

These access points will be complemented by public bathroom facilities and showers as well as stricter regulations on construction and development in the region. These efforts in combination with new noise ordinances and stricter enforcement of environmental regulations are already starting to have a positive impact on Tulum’s growth and long term sustainability.