December 2022 - News
Happy Holidays to our Aflora Tribe! As we near the end of an eventful year we express deep gratitude to our dedicated community and to the incredible efforts of the builders and creators that have transformed the dream of Aflora into a spectacular reality. As we push to make-up for delays our subcontractors are now operating on extended schedules, with work continuing into nights, weekends and holidays.
Our onsite supervision is present 7-days a week to ensure progress is made.
Construction Progress
Work continues on all key areas of Aflora. We summarize the major work ongoing in each area below
Magic Apartment Towers
Tower A:
Construction progress - 79% Complete
Final floors poured
Preparations for final finish in interiors and exteriors
Detailing on exterior elements
Drainage installation and waterproofing in rooftop gardens
Installation of rooftop pergolas
Installation of machine rooms and pool equipment
Tower B:
Construction progress - 78% Complete
Final floors poured
Preparations for final finish in interiors and exteriors
Detailing on exterior elements
Drainage installation and waterproofing in rooftop gardens
Installation of rooftop pergolas
Installation of machine rooms and pool equipment
Tower C:
Construction progress - 58% Complete
Rooftop pools poured
Rooftop level floors completed
Detailing on rooftop access stairs
Tower D:
Construction progress - 27% Complete
2nd level walls in progress
1st level installations in progress
Structural preparations for upper levels underway
Tower I:
Construction progress - 21% Complete
Elevator shaft poured
2nd level floors in progress
Installations on lower levels
Villa 1:
Construction progress - 90% Complete
Sheetrock installation
Kitchen and Closet Cabinetry
Steel supports for stairs, gates, and exterior doors
Patios and Terraces
Installation of oversized glass panes
Loft Village:
Construction progress - 91% Complete
Polished cement interior finishes
Polished cement floors
Kitchen and Closet Cabinetry
Countertops and vanity installed
Bathroom shower tile installation
Terrace shade-panels installed
Final detailing in Phase 1 units
Lobby:
Construction progress - 92% Complete
Carpentry installed in upstairs office
Polished cement floors in office completed
Lighting preparations installed
Polished cement floors in office completed
Panza (Restaurant):
Construction progress - 83% Complete
Kitchen extraction and counter-incendiary systems installed
Gas lines installed & tested
Craft Cocktail Bar & Open Kitchen Area constructed and awaiting the installation of wood fired oven
Wellness Tower:
Construction progress - 60% Complete
2nd level access stairs in progress
2nd level structure in progress
Rehabilitation of Green Areas in surrounding vicinity
Frontal Sculptural Wall:
Construction progress - 100% Complete
Full length of perimeter completed
Foundations treated against moisture
Surrounding in-fill and landscaping underway
Temporary construction walls removed
Service Areas & Bodegas:
Construction progress - 60% Complete
Walls and structural elements completed
Final roof levels underway
Installations of electrical and hydro sanitary network completed
Semi-Olympic Pool:
Construction progress - Awaiting final finish
All preliminary works completed and tested
Surrounding pool deck and cobblestoned area in progress
Awaiting the termination of construction to apply final EKOL finish to prevent accidental damage or wear.
Natural Pool:
Construction progress - Awaiting final installations
Dredging of fine material and debris underway with specialized SCUBA team
Natural circulation system to decrease maintenance costs
Surrounding leveling and landscaping in progress
BathHouse & Spa:
Construction progress - Preliminary Site preparations
Green Initiative
We are thrilled to see the results of our conservation efforts as we integrate transplanted trees and native species into their final locations, rehabilitating areas previously cleared for construction. Our in-house team of native plant specialists take extra care to integrate symbiotic species suitable environments, using composted material sourced on-site to ensure successful long-term growth.
Community News
Big plans are underway in Tulum for the year 2023. Municipal officials announced sweeping measures to improve the excess and visitor experience at Tulum’s public beach and National Park area. With the relocation of over 170 irregular tourist-servers ranging from coconut vendors to snorkel tours, the municipality plans to add 3 additional beach access points in this year alone.
These access points will be complemented by public bathroom facilities and showers as well as stricter regulations on construction and development in the region. These efforts in combination with new noise ordinances and stricter enforcement of environmental regulations are already starting to have a positive impact on Tulum’s growth and long term sustainability.