Work in progress - February 2023
Hello to our beautiful tribe! We are excited to share our progress this month as we unveiled our first fully furnished showroom this month. Located in our Wonder Loft Village, our showroom gives future residents and potential investors a taste of the unique and carefully curated interiors of Aflora's living spaces.
Construction Progress
Work continues on all key areas of Aflora. We summarize the major work ongoing in each area below
Loft Village:
Construction progress - 94% Complete
Villa 1:
Construction progress - 93% Complete
Tower B:
Construction progress - 79% Complete
Final floors poured
Preparations for final finish in interiors and exteriors
Detailing on exterior elements
Drainage installation and waterproofing in rooftop gardens
Installation of rooftop pergolas
Installation of machine rooms and pool equipment
Tower D:
Construction progress - 37% Complete
2nd level walls in progress
1st level installations in progress
Structural preparations for upper levels underway2nd level walls in progress
Tower A: Construction progress - 80% Complete
Final floors poured
Preparations for final finish in interiors and exteriors
Detailing on exterior elements
Drainage installation and waterproofing in rooftop gardens
Installation of rooftop pergolas
Installation of machine rooms and pool equipment
Tower C:
Construction progress - 61% Complete
Rooftop pools poured
Rooftop level floors completed
Detailing on rooftop access stairs
Elevator cube complete
Tower I:
Construction progress - 28% Complete
Elevator shaft poured
2nd level floors in progress
Installations on lower levels
Service Areas & Bodegas:
Construction progress - 65% Complete
Walls and structural elements completed
Final roof levels underway
Installations of electrical and hydro sanitary network completed
Semi-Olympic Pool:
Construction progress - Awaiting final finish
All preliminary works completed and tested
Surrounding pool deck and cobblestoned area in progress
Awaiting the termination of construction to apply final Pebbletec finish to prevent accidental damage or wear.
Natural Pool:
Construction progress - Awaiting final installations
Dredging of fine material and debris underway with specialized SCUBA team
Natural circulation system to decrease maintenance costs
Surrounding leveling and landscaping in progress
Integration of waterfall and water features
Lobby:
Construction progress - 95% Complete
Installation of dynamic art in progress
Panza (Restaurant):
Construction progress - 88% Complete
Kitchen extraction and counter-incendiary systems installed
Pizza oven installation in progress
Craft Cocktail Bar & Open Kitchen Area constructed and awaiting final finishes
Wellness Tower:
Construction progress - 62% Complete
2nd level access stairs in progress
2nd level structure in progress
Rehabilitation of Green Areas in surrounding vicinity
BathHouse & Spa:
Construction progress - Preliminary Site preparations
Community News
This month head of FONATUR Javier May announced additional information regarding the ongoing Maya Train project. May announced that once completed, the rail network and train system will be amongst the best in the world in terms of service and technology, with internet connectivity and surveillance throughout the entire project.