Work in progress - March 2023

Aflora is coming to life with units receiving final touches before decoration and delivery begins. As we work diligently on Phase 1 units we are taking special care to ready amenities and rehabilitate common areas with native vegetation and landscaping. As seasonal rains commence we are able to observe and optimize the functionality of our bioclimatic designs. 

 This month we also celebrate progress on the long-awaited connections to municipal services such as water, electricity, and drainage. Thanks to the hard work of our teams we have been able to expedite these processes which are essential to the functionality of our community. 

Construction Progress

Work continues on all key areas of Aflora. We summarize the major work ongoing in each area below


Loft Village: Construction progress - 95% Complete


Essence Luxury Villas

Villa 1 Construction progress - 95% Complete

  • 20 of 68 units delivered to interior design team

  • Installation of stoves & ceiling fans

  • Countertops and vanities

  • Built-in gardens

  • Terrace guard rails

  • Installations of toilets and accessories 

  • Testing of hot water heaters

  • Final detailing in Phase 1 units  

Villa 5 Construction progress - 11% Complete

  • Foundations excavated and foundation elements in progress


Magic Apartment Towers

Tower B:
Construction progress -81% Complete

  • Final floors poured 

  • Detailing on exterior elements

  • Drainage installation and waterproofing in rooftop gardens

  • Installation of glass windows and sliding doors

  • Installation of machine rooms and pool equipment  

      

Tower D:
Construction progress - 45% Complete

  • 4th level walls in progress 

  • 1st & 2nd level installations in progress

Tower H:
Construction progress - 45% Complete

  • Walls and ceilings prepared on level 1

  • Installations in floors and ceilings on level 1

Tower A: Construction progress - 82% Complete

  • Preparations for final finish in interiors and exteriors 

  • Installation of garden-level cobblestone blocks

  • LP gas lines and meters installed

  • Installation of COREV on exteriors

  • Installation of railing on terraces

Tower C:
Construction progress - 65% Complete

  • Preparations for final finishes

  • Detailing on rooftop levels

Tower I:
Construction progress - 34% Complete

  • Elevator shaft poured on level 3

  • 3rd level walls in progress

  • Installations on lower levels in progress

Service Areas & Bodegas:
Construction progress - 68% Complete   

  • Testing of installations in progress

  • Final floors poured

Semi-Olympic Pool:
Construction progress - Awaiting final finish

  • Integrated gardens planted with native palm trees

Natural Pool:
Construction progress - Awaiting final installations

  • Construction of stone steps and retaining walls made from material sourced on-site

  • Fiber optic lighting network installed

  • Integration of waterfall and water features 

Lobby:
Construction progress - 97% Complete

  • Interior lighting installed

Panza (Restaurant): 
Construction progress - 90% Complete

  • Carpentry and doors in bathrooms in stalled

  • Exterior lighting installed

  • Kitchen prepped and cleaned awaiting equipment install

Wellness Tower:
Construction progress - 65% Complete  

  • Final level undergoing completion

  • Installations on lower levels

  • Rehabilitation of Green Areas in surrounding vicinity


Green Initiative

This month the Tulum Municipality announced an initiative to create a new and improved landfill to accommodate the large growth in the region and minimize ecological impacts of the soon-to-be-constructed airport.

 We look forward to participating in a greener future for Tulum as we implement sustainable waste management methods in our multiple disposal areas throughout the community 

Community News

It is with a heavy heart that we report the passing of our Municipal Mayor, Marciano Dzul Caamal, who suffered complications from his ongoing battle with cancel. Marciano was fundamental in creating and overseeing a vast number of public works projects and municipal improvements. His successor, Diego Castañón Trejo, has promised to continue these efforts and fulfill Marciano's dream of a better Tulum for all. 