Work in progress - March 2023
Aflora is coming to life with units receiving final touches before decoration and delivery begins. As we work diligently on Phase 1 units we are taking special care to ready amenities and rehabilitate common areas with native vegetation and landscaping. As seasonal rains commence we are able to observe and optimize the functionality of our bioclimatic designs.
This month we also celebrate progress on the long-awaited connections to municipal services such as water, electricity, and drainage. Thanks to the hard work of our teams we have been able to expedite these processes which are essential to the functionality of our community.
Construction Progress
Work continues on all key areas of Aflora. We summarize the major work ongoing in each area below
Loft Village: Construction progress - 95% Complete
Essence Luxury Villas
Magic Apartment Towers
Tower B:
Construction progress -81% Complete
Final floors poured
Detailing on exterior elements
Drainage installation and waterproofing in rooftop gardens
Installation of glass windows and sliding doors
Installation of machine rooms and pool equipment
Tower D:
Construction progress - 45% Complete
4th level walls in progress
1st & 2nd level installations in progress
Tower H:
Construction progress - 45% Complete
Walls and ceilings prepared on level 1
Installations in floors and ceilings on level 1
Tower A: Construction progress - 82% Complete
Preparations for final finish in interiors and exteriors
Installation of garden-level cobblestone blocks
LP gas lines and meters installed
Installation of COREV on exteriors
Installation of railing on terraces
Tower C:
Construction progress - 65% Complete
Preparations for final finishes
Detailing on rooftop levels
Tower I:
Construction progress - 34% Complete
Elevator shaft poured on level 3
3rd level walls in progress
Installations on lower levels in progress
Service Areas & Bodegas:
Construction progress - 68% Complete
Testing of installations in progress
Final floors poured
Semi-Olympic Pool:
Construction progress - Awaiting final finish
Integrated gardens planted with native palm trees
Natural Pool:
Construction progress - Awaiting final installations
Construction of stone steps and retaining walls made from material sourced on-site
Fiber optic lighting network installed
Integration of waterfall and water features
Lobby:
Construction progress - 97% Complete
Interior lighting installed
Panza (Restaurant):
Construction progress - 90% Complete
Carpentry and doors in bathrooms in stalled
Exterior lighting installed
Kitchen prepped and cleaned awaiting equipment install
Wellness Tower:
Construction progress - 65% Complete
Final level undergoing completion
Installations on lower levels
Rehabilitation of Green Areas in surrounding vicinity
Community News
It is with a heavy heart that we report the passing of our Municipal Mayor, Marciano Dzul Caamal, who suffered complications from his ongoing battle with cancel. Marciano was fundamental in creating and overseeing a vast number of public works projects and municipal improvements. His successor, Diego Castañón Trejo, has promised to continue these efforts and fulfill Marciano's dream of a better Tulum for all.