Work in progress - June 2024

Life in Aflora

Summer has arrived in Tulum along with an unseasonably early rains. With more than 10-consecutive days of heavy rain, we have been working around the clock to prepare the installations of Aflora against future tropical storms.

 

These meteorological events have incurred delays in certain areas, however we are finalizing installations on our onsite power plant and back-up systems that will assist us in providing energy to key areas in the event of blackouts and power cuts.

Construction Progress


Work continues on Aflora. 

Villa 5:

Construction progress - 67% Complete

  • Sheetrock supports installed

  • Cables and electrical connections installed

  • Patio installed

  • Metal railing installed and painted

Magic Apartment Towers

Tower A:

Construction progress - 99% Complete

  • Final units in process of delivery 

Tower B:

Construction progress - 99% Complete

  • Final units in process of delivery

Tower C:

Construction progress - 99% Complete

  • Final units in process of delivery

Tower D:

Construction progress - 89% Complete 

  • Detailing in carpentry

  • Preparations for interior design installation

  • Detailing of pergolas and lateral facades

  • Installation of air conditioning equipment completed

Tower H:

Construction progress - 65% Complete

  • Installation of tiles in bathrooms

  • Installation of pergolas on rooftop levels

  • Garden level cobblestone installed

Tower I:

Construction progress - 67% Complete

  • Preparations for window installation underway

  • Plumbing installations connected with the main hydrosanitary grid

  • Railings installation in progress

Natural Pool:

Construction progress - Awaiting final installations

  • Installation of landscaping and illumination of paths

  • Waterfalls in operation

BathHouse & Spa:

Construction progress - Under Revision

Green Initiative

Tulum received historic figures of rainfall for this month, setting records not previously seen in the past 72 years in the region. 

 

We are pleased to report that our investment in permeable materials has been a tremendous success, resulting in no standing water or flooding in our common areas. By respecting the porosity of the region's geography, our common areas allow for the rain to replenish the natural aquifers.

Community News

After two years of work and 2.5 billion pesos of investment, the Jaguar National Park of Tulum is finally nearing completion. The park, currently 92% finished, includes the creation of six beach access points, trails to the archaeological zone, and the construction of bike and walking paths.

 

This month Tulum Mayor Diego Castañón Trejo has laid the first stone for the municipality’s new Command, Control, Communication and Computing Center. The new initiative will cost around 28.3 million pesos and benefit 33,000 residents with advanced technology for crime prevention. 

Previous
Previous

Work in progress - August 2024

Next
Next

Work in progress - May 2024