Work in progress - May 2023
This month we are excited to unveil our continued progress within our community. As new residents receive their bespoke homes, we finalize details on surrounding amenities and green areas, ensuring that every element harmonizes with our intentional designs. Using dynamic creative processes we supervise daily advances, optimizing lighting, pathways, vegetations, and decor to create stunning results. As we enter the rainy season we make sure to take advantage of the local climate to test irrigation and site levels as well as waterproofing in all construction areas.
Construction Progress
Work continues on Aflora. We summarize the major advances in each area below
Loft Village: Construction progress - 98% Complete
Essence Luxury Villas
Magic Apartment Towers
Tower B:
Construction progress -84% Complete
Detailing on exterior elements
Drainage installation and waterproofing in rooftop gardens
Installation of climate control systems
Showroom carpentry in progress
Installation of machine rooms and pool equipment
Tower D:
Construction progress - 53% Complete
Machine rooms for pools in progress
Roof-level installations in progress
Rooftop pools and gardens in progress
Tower H:
Construction progress - 35% Complete
Walls and ceilings complete on level 2
Installations in floors and walls on level 3
Tower A: Construction progress - 84% Complete
Preparations for final finish in interiors and exteriors
Installation of garden-level cobblestone blocks
Installation of rooftop pergolas
Installation of climate control systems
Installation of final floor in circulations areas and stairs
Tower C:
Construction progress - 66% Complete
Terrace railings installed
Detailing on rooftop levels
External hydraulic connections completed
Tower I:
Construction progress - 48% Complete
Interior stairs poured on level 4
4th level walls in progress
Installations on lower levels in progress
Rooftop pools in progress
Service Areas & Bodegas:
Construction progress - 74% Complete
Testing of installations in progress
Server rooms completed and awaiting equipment
Doors and windows installed
Climate control in progress
Semi-Olympic Pool:
Construction progress - 99%
Integrated gardens planted with native palm trees
Final finish completed and sealed
Natural Pool:
Construction progress - Awaiting final installations
Construction of stone steps and retaining walls made from material sourced on-site
Waterfall undergoing testing
Lobby:
Construction progress - 99% Complete
Lobby office complete
Final detailing on bamboo facade
Panza (Restaurant):
Construction progress - 98% Complete
Testing of kitchen equipment
Exterior patio detailing in progress
Bar completed
BathHouse & Spa:
Construction progress - 5%
Foundations completed
Lower level structure in progress
Wellness Tower:
Construction progress - 69% Complete
Application of interior and exterior finishes
Installations on lower and upper levels in progress
Community News
This month President Andrés Manuel López Obrador announced that the Tulum International Airport will be operational as soon as December of this year. This comes shortly after an announcement that construction progress on the airport is now past 40%.
We also celebrate Tulum's 15 year anniversary this month, as we reflect back on the rapid growth and progress that has occurred in that time. The celebration was culminated with a special performance by Mexico's renowned group Los Angeles Azules in a well attended municipal event in held in Tulum's Deportivo.