Work in progress - April 2024

April marks another successful month in our growing community, as we see increasing attendance in our yoga, dance, and fitness classes as well as sold-out theater shows and live music events in PANZA.

With the launch of Tulum's first Residence Club, Aflora is now becoming accessible to a wider range of individuals. Our revolutionary Co-Ownership Model allows community members to share ownership of luxurious, private residences and enjoy abundant and flexible lodging in their elegant homes throughout the year. Get in touch with our onsite team to join our exclusive program!

Community News

Tulum's international connectivity continues to expand with newly announced direct flights to the United States and surrounding Latin American destinations. With new direct flights this from the southern US, Mexico City, and Panama City, we are quickly witness a huge increase in global tourism to our local region. 

 For Tulum residents this means a significant rise in international business but also greater accessibility to the countless destinations, making our quickly growing town the perfect home for the new class of digital nomads and experiential lifestyle seekers. 

Green Initiative

As we prepare for the seasonal influx of sargassum a variety of seaweed, the Secretary of the Navy reports that 8,600 meters of anti-sargassum barriers are being placed off Quintana Roo beaches.

 For the 2024 sargassum season, the state of Quintana Roo will have four beach sweepers, 22 small vessels, 11 collectors, an ocean vessel and eight amphibious bands to compact the sargassum.

Construction Progress

Work continues on Aflora. As we transition to our in-house construction supervision team we have been diligently reassessing each area. 

Villa 5:

Construction progress - 60% Complete

  • Installation of railings in terraces 

  • Rooftop floors in progress

  • Garden wall in progress

Magic Apartment Towers

Tower A:

Construction progress - 99% Complete

  • Final units in process of delivery 

Tower B:

Construction progress - 97% Complete

  • Final units in process of delivery

Tower C:

Construction progress - 97% Complete

  • Ground-floor units in process of delivery

  • Final detailing carpentry

  • Detailing on exterior finish elements

  • System of electrical grounding completed

Tower D:

Construction progress - 67% Complete 

  • Installation of windows in progress 

  • Installation of railings  in terraces

  • Installation of final floors in access areas

Tower H:

Construction progress - 61% Complete

  • Continuation of interior finishes in progress

  • Rooftop primary finishes in progress

Tower I:

Construction progress - 63% Complete

  • Continuation of interior finishes in progress

  • Rooftop primary finishes in progress

Natural Pool:

Construction progress - Awaiting final installations

  • Construction of additional paths and viewpoints with landscaping

  • Waterfalls in operation

BathHouse & Spa:

Construction progress - Under Revision