Work in progress - March 2024

Work continues on Aflora. As we transition to our in-house construction supervision team we have been diligently reassessing each area. 

Green Initiative

As we enter the Spring season we take extra care to respect the nesting animals of the region. With the many species of endemic and migratory birds that nest locally, our workers are given specific instructions not to disturb potential nesting areas. We are also careful and considerate of crocodiles and tortoises which make their nests in the low jungle. 

Community News

Tulum's shopping-options are growing by the day with the announcement of a new Soriana Hiper market. The supermarket which is currently under construction at kilometer 0.5 on the Tulum-Cobá highway will have a large shopping gallery, self-serve checkouts, covered parking and offer a wide range of international and domestic products. 

Construction Progress

Villa 5:

Construction progress - 57% Complete

  • Fan & coil climate system installation in progress

  • Stairway in progress

  • Garden wall foundations completed

Magic Apartment Towers

Tower A:

Construction progress - 99% Complete

  • Final units in process of delivery 

Tower B:

Construction progress - 97% Complete

  • Final units in process of delivery

Tower C:

Construction progress - 88% Complete

  • Exterior finishes in final stages

  • Detailing on polished cement and carpentry

  • Sealant of cement floors underway

Tower D:

Construction progress - 63% Complete 

  • Application of floors and tiles

  • Installation of pergolas in Penthouse units 

  • Testing of drainage and waterproofing in progress

Tower H:

Construction progress - 60% Complete

  • Primary layer of interior finishes in progress

  • Roof garden primary finishes in progress

Tower I:

Construction progress - 62% Complete

  • Primary layer of interior finishes in progress
    Roof garden primary finishes in progress

Wellness Tower:

Construction progress - 100% Complete  

 

Natural Pool:

Construction progress - Awaiting final installations

  • Construction of stone paths and viewpoints with landscaping

  • Additional waterfalls in progress

BathHouse & Spa:

Construction progress - 45%

  • Access stairs in progress

  • Sealing and testing of cisterns

  • Steel structural tests in progress