Greeting to our beautiful community! Big changes are underway onsite as we transition our construction supervision team to an in-house operation in order to ensure better quality control and stricter deadlines for our final phases of construction. Additionally, we have formed a team of specialists to attend to detail work and preventative maintenance within construction areas. We are working hand-in-hand with the Condominium Administration Team as they begin to operate common areas and amenities to ensure our community operates to the highest standards.

 It has been an absolute pleasure to welcome Aflora's first resident artist, Dubai-based photographer Marta Lamovsek, as well as host our first musical interventions in Panza Dining & Bar. We are thrilled to announce an exciting line-up of events and cultural programming for the coming months!

Construction Progress

Work continues on Aflora. As we transition to our in-house construction supervision team we have been diligently reassessing each area. 

Areas with unchanged percentages are still under revision, we appreciate your patience as we revise our construction progress.

Loft Village:

Construction progress - 100% Complete

  • Preventative maintenance ongoing

Villa 5:

Construction progress - 65% Complete

  • Sheetrock installation in progress

  • Rooftop pool finishes in progress

Magic Apartment Towers

Tower A:

Construction progress - 100% Complete

  • Preventative maintenance in progress

  • Unit deliveries in progress

  • Landscaping in progress

Tower B:

Construction progress - 100% Complete

  • Preventative maintenance in progress

  • Unit deliveries in progress

  • Landscaping in progress

Tower C:

Construction progress - 78% Complete

  • Re-testing of hydraulic installations

  • Rooftop pergolas in progress

  • Carpentry installation underway

Tower D:

Construction progress - 63% Complete 

  • Revision and testing of drains and pools

  • Re-testing of hydraulic installations

  • Rooftop finishes in progress

Tower H:

Construction progress - 60% Complete

  • Preparations for finishes in common areas and stairwells

  • Preparations for handrails and balcony rails

Tower I:

Construction progress - 62% Complete

  • Phase II showroom in progress

  • Testing of rooftop pools

Wellness Tower:

Construction progress - 100% Complete  

  • Interior design team finalizing decor

  • Final cleaning in progress

  • Landscaping complete

Natural Pool:

Construction progress - Awaiting final installations

  • Preventative maintenance and cleaning in progress

  • Additional waterfalls & circulation installed

BathHouse & Spa:

Construction progress - 46%

  • Anti-corrosive finishes applied to external steel-support structure 

  • Testing on cisterns in progress

  • Preparations for equipment in progress

Green Initiative

With the opening of Tulum's International Airport, municipal and federal efforts are underway to mitigate the increasing congestion of traffic within the town of Tulum. Local efforts are in progress to increase pedestrian mobility while a highway bypass is in the works to redirect heavy vehicles through an alternative route.   

Community News

As Tulum continues to develop and grow, local investment efforts in education are in full swing. Nearly 100 million pesos has been invested in educational institutions in Tulum this year, with 30 million spent for the construction of a new education facility for 270 students.

 

The new Tulum Jaguar National Park has been set to open by April of this year. Located directly across the avenue from Aflora, the National Park will boast over 1000 hectares of protected area as well as museums, walking trails, cultural attractions, and viewpoints for observing nature. 

Previous
Previous

Work in progress - March 2024

Next
Next

Work in progress - January 2024